Tentative Timeline

6/08 – 10/08 Construction plans created
10/08 – 11/08 Final budget approval
11/08 – 12/08 Permitting process
11/08 – 12/08 2nd floor move out
12/08 – 2/09 2nd floor construction*
2/09 Basement move out
2/09 – 5/09 Basement construction
5/09 1st floor move out
5/09 – 8/09 1st floor construction*

*No active construction during December or May’s reading periods.

Project Highlights

Study Space

· Creates a 24/7 study space

· Increases # of sq. ft. for study space

· Increases # of group study rooms

· Provides better sound proofing to reduce noise

· Designates silent study area

Collection Access

· Increases collection potential by using compact shelving

· Makes basement collection more accessible with addition of staircase

· Corrects humidity problems in the basement

Environment

· Improves lighting

· Provides new carpeting

· Updates some furnishings

· Improves ADA accessibility

Draft Floor Plans -

Click to download a pdf.

Basement Plan 1st Floor Plan 2nd Floor Plan


Posting your comment.

  • Dewey Second Floor

    Photo by Daniel Eppelsheimer

  • Hours

    Dewey Library will be open during the construction; see our Hours.
  • Comments?

    Email ReDew@mit.edu.
  • Archives

    • November 2009
    • July 2009
    • May 2009
    • April 2009
    • February 2009
    • January 2009
    • December 2008
    • November 2008
    • October 2008
    • September 2008
    • August 2008
  • This Site

    Site admin
    Subscribe to RSS feed for updates

Text licensed under Creative Commons, unless otherwise noted. All other media all rights reserved unless otherwise noted.
WordPress Theme based on Light Theme