Timeline & Plans
Tentative Timeline
| 6/08 – 10/08 | Construction plans created |
| 10/08 – 11/08 | Final budget approval |
| 11/08 – 12/08 | Permitting process |
| 11/08 – 12/08 | 2nd floor move out |
| 12/08 – 2/09 | 2nd floor construction* |
| 2/09 | Basement move out |
| 2/09 – 5/09 | Basement construction |
| 5/09 | 1st floor move out |
| 5/09 – 8/09 | 1st floor construction* |
|
*No active construction during December or May’s reading periods. |
|
Project Highlights
|
Study Space |
|
|
|
· Creates a 24/7 study space |
|
|
· Increases # of sq. ft. for study space |
|
|
· Increases # of group study rooms |
|
|
· Provides better sound proofing to reduce noise |
|
|
· Designates silent study area |
|
|
|
|
Collection Access |
|
|
|
· Increases collection potential by using compact shelving |
|
|
· Makes basement collection more accessible with addition of staircase |
|
|
· Corrects humidity problems in the basement |
|
|
|
|
Environment |
|
|
|
· Improves lighting |
|
|
· Provides new carpeting |
|
|
· Updates some furnishings |
|
|
· Improves ADA accessibility
|
Draft Floor Plans -
Click to download a pdf.